Construction of the Basseterre Desalination Plant Progresses as the Fusing of Intake Lines Begins

Date:

Basseterre, St. Kitts (MoPIEUDT NEWS) – On Monday, April 7, 2025, MoPIEUDT News returned to the Basseterre Desalination Plant to check in with the Site Supervisor Ben Moise concerning the progress on the pipeline.

Ben worked alongside a handful of his team, surrounded by an array of heavy metal pipes near an operating fusion machine. He explained the crew’s activity.

Site Supervisor Ben Moise

Basseterre Desalination Plant Site Supervisor Ben Moise Comments on Progress at the Site

On Wednesday, April 9, Assistant Water Engineer at the St. Kitts Water Services Department (WSD), Chantal Hanley, spoke briefly about the connectivity between the desalination plant and the storage tank at Morne Peak during her appearance on the WSD’s bi-monthly radio show, The Water Line.

“Currently, we are making good progress. [We] have reached quite far, almost to the top by the reservoir. Right now, [we] are at Bird Rock putting in pipeline.”

– WSD Assistant Water Engineer Chantal Hanley

The construction of the desalination plant is scheduled for July 2025.

Latest Articles

Related articles

Water Service Interruption – Beacon Heights and Dewars

Basseterre, St. Kitts (MoPIEUDT NEWS) - The St. Kitts Water Services Department (WSD) regrets to inform the general...

WSD: Service Interruption Notice – Lime Kiln to New Guinea

Basseterre, St. Kitts (MoPIEUDT NEWS) – The St. Kitts Water Services Department (WSD) informs the general public of a...

WSD: Notice of Low Water Pressure & Service Interruption in Cedar Grove

Basseterre, St. Kitts (MoPIEUDT NEWS) - The St. Kitts Water Services Department (WSD) regrets to inform residents at...

WSD Temporarily Suspends Bill Payments at Post Office for World Post Day 2025

Basseterre, St. Kitts (MoPIEUDT NEWS) - The St. Kitts Water Services Department (WSD) advises the general public that...
Call Now Button